https://test-backlink-1.blogspot.com/ https://test-backlink-2.blogspot.com/ https://test-backlink-3.blogspot.com/ https://test-backlink-4.blogspot.com/ https://test-backlink-5.blogspot.com/ https://test-backlink-6.blogspot.com/
paviprogress Archives - Bethany Birches Camp

Posts Tagged ‘paviprogress’

Wood Boiler Update

The boiler has been running for a few months now and it can heat (we have burned 6 cords which is all we set aside for this winter)!  These two video updates from Tuna demonstrate the latest.  Summary: the boiler can heat the cabin in addition to the pavilion (if we burn lots of wood).

Two months later, test # 2. Not only can it heat multiple buildings, it doesn’t burn as much wood after some programming changes!

You can see the photo/video album of the project here: https://www.icloud.com/sharedalbum/#B0f5n8hH4GTJMha

Spring Work Day

Summer programming starts in a month! We want to have occupancy to the pavilion by the end of the month. Can you help?!

Join us on Saturday May 28th from 9am – 3pm for Spring Work Day! Jobs will include (but not limited to)
.Painting the upstairs of the pavilion
.Turning the pavilion from a construction zone to summer camp zone
.Putting away/Cleaning up winter camp equipment
.Preparing Shelter Sites for Summer
.Preparing grounds for summer camp

We’ll have jobs for all skill levels and lunch for everyone, too!
Russell “OWO” Pejouey will be on site to cook a delicious lunch.

Lodging is available here at Bethany Birches for anyone who wants to come from a distance or make a weekend of it!

Email amber at bethanybirches.org to let us know you can help or respond on the BBC Facebook Page: https://www.facebook.com/events/568154376678577/

 

Volunteers Invite Friends to Camp

I’ve been struck the last few days how much fun it is to bring friends to camp! This past week 2 volunteers who have been coming to camp for the past 18+ years brought two friends to camp. Each of them contributed to help the 2nd floor of the pavilion progress.

Merle Horst and Dave Mussleman are part of the Musser Woodcutting crew. This crew of guys have been cutting the camp’s wood for the last 18+ years. A few weeks ago I sent an email to Merle to see if he could round up some able volunteers to help us finish the 2nd floor of the pavilion. Dave was available and so were 2 friends – Lester and Will.

Thanks to Merle and Dave inviting friends a lot MORE was accomplished in 2 and a half days on the top floor of the pavilion. Beautiful barn doors, trim, wainscot caps, shelves were among their projects. Not to mention everyone seemed to have a lot of fun! Community building happens among campers, volunteers, staff and whoever finds themselves on the hill. Camp is always more fun with friends!

If you’re a camper family – consider inviting at least 1 new friend to BBC this summer!
If you’re a volunteer – consider inviting a friend who’s never been to camp to join you the next time you’re on the hill!

We hope to see you on the hill soon!

Cheeks.

IMG_8959

The sawing station

IMG_8958

Lester and Will work on shelving

IMG_8957

Pine Trim Everywhere

IMG_8956

Shelf and Coat Rack at the Main Entrance

IMG_8950

Dave putting up Barn Board Trim

IMG_8949

Rustic Shelving above office doors

IMG_8945

Friends from Lancaster helping at BBC!

IMG_8954

Having a good time

Ongoing Pavi Volunteer Opportunities

BBC continues to be an exciting place to be in the winter. With and without snow! Thanks to the doors being installed in the new pavilion snow camps are exciting and fun even with limited snow.

Can you help us continue to move towards a finished pavilion? This time it’s in a slightly different form than a traditional work day.

Do you have an hour or 3 to give to the pavilion progress efforts over the course of the next 2 weeks? Pavilion Progress will continue during the weeks between snow camps with the following projects:

– Staining pine boards for the upstairs ceiling and the garage door interior siding.
– Painting the walls of the 2nd floor.

Staining/Painting will be set up in between snow camps. If you can come for a chunk of time on any of the following days, please let me know and we’ll be ready for you! No prior experience required.

Tues Feb 23 – Thurs Feb 25: 9:30am – 4pm

Tues Mar 1 – Sat Mar 5: 9:30am – 4pm

While the format is different we’ll still plan to have coffee, snacks and lunch for you if we know you are coming. Email amber at bethanybirches.org to let us know when you can help!

We are so thankful for your help! Hope to see you on the hill soon,

Amber “Cheeks” Bergey

Volunteer to Help Finish the Pavilion at BBC – Feb 6th

2016 is off to a good start at BBC! Framing for the big doors is happening, an inaugural fire was lit in the pavilion fireplace and drywall on the 2nd floor is almost complete. Can you help us keep going?!

Join us on Feb 6th to keep making progress on the 2nd floor of the pavilion AND to transform the pavilion from a construction zone to a snow camp zone! We’ll have work for skilled (hanging pine boards, trim, etc) and unskilled (painting, clean up, organizing, etc) volunteers alike. Coffee Break, Lunch (12:30) and a tubing break for all as well! Please let us know you’re coming so we can plan projects and lunch accordingly. (amber at bethanybirches dot org or call the office 802-672-5220)

The fun will start at 9am. Come for an hour or come for the day.

If you can’t join us on the 6th but would still like to help, please let us know. There are various projects that can be done outside of work days if you have other time you are able to give.
OR if you have a group you’d like to bring for a few days we’d be happy to coordinate that as well.
We are so thankful for your help! Hope to see you on the hill soon,

Amber “Cheeks” Bergey

work day pic

Pavilion Work Continues – Can you help?!

Happy New Year from BBC!

What better way to start the new year than helping build the pavilion at BBC?! There is still lots of work to do on the 2nd  floor of the pavilion including drywall, finishing work, hanging doors and shelving (see pic below). We’d love to have your help!
Join us on January 16th to make progress on the 2nd floor. We’ll start working at 9am with snacks/coffee available all day and lunch at 12:30. Join us for the whole day or just an hour! Specific work
will depend on what skill is available. PLEASE LET US KNOW if you are coming so Phil Wilkerson (construction manager) can plan projects accordingly.
If you can’t join us on the 16th but would still like to help, please let me know. There are various projects that can be done outside of work days if you have other time you are able to give.
OR if you have a group you’d like to bring for a few days we’d be happy to coordinate that as well.

We are so thankful for your help! Hope to see you on the hill soon,

Amber “Cheeks” Bergey

Upstairs unfinished IMG_1898

Pavilion Progress Continues – Can you help?!

Happy December from BBC!

Work on the pavilion continues!  We hope to have the 2nd floor of the pavilion completed and usable by April of 2016. The 2nd floor includes office space, a large meeting room, the nurses station, etc. We’re hoping to utilize as much volunteer labor as possible. Can you help? See the details below and write to amber@bethanybirches.org or call the camp office at 802-672-5220 to let us know if you can help!
Join us on Saturday, Dec 12. The work will start at 9am with lunch at noon and continue until 3ish. Snacks, coffee and treats available throughout the day. All work will be inside!

Come for all of the day or come for an hour but PLEASE LET US KNOW IF YOU CAN COME. This will help Phil Wilkerson plan what work can be done.
Contact amber@bethanybirches.org or call the camp office 802-672-5220 to let us know you plan to join.
If you can’t come on the 12th keep your eyes pealed for the next pavi work day in early January.
If you’ve got a couple days you’d like to give or a group of people who’d like to help let us know. There is plenty to do in the hopes we can have the top floor finished by April.
Thanks for your ongoing support. For an up to date report on the pavilion progress check out this link: http://www.bethanybirches.org/mission-possible/
Thanks for your help!
Volunteers have already begun working on the 2nd floor

Volunteers have already begun working on the 2nd floor

LarryDerstine FBPavilion profile shot

 

 

Construction Update – Week of June 8

This week has been stressful! We had an electrical inspection on Monday (passed). Building inspection on Tuesday (allowed access to a couple areas). We are still needing a visit from the health department.  And, on top of that, staff are showing up.  In fact, summer staff orientation starts on Saturday!

In the building lots of progress has happened.  Wall finishes are going on.  Fire alarm has been completed. The kitchen is almost entirely set up (and is now being clean).  Final grading and seeding has happened everywhere. Porch railings are being installed.  The boiler is supposed to come on line Friday.

And yet, there is still lots to do.  Some lighting fixtures have to be installed and there is plenty of finish carpentry to do. And of course after that, the upstairs has to be finished, chimney installed, big garage doors and wood boiler installed, climbing wall built and some other things.  But, we are headed toward completion on phase 1 and that feels good.

Check out the latest photos.

Pavi Construction Update April 1-30

What a month! The pavi has been transformed from a partly finished shell to an almost summer-ready building…well, parts of it.

Progress could not be made without the help of so many volunteers! People have come from far (PA) and close (Lynds Hill Road) to help get the pavi ready for Summer 2015.

Progress also could not be made without the daily efforts of the Jenne Construction Crew. We’re thankful they braved the mud season & cold spring temps to keep moving the pavilion closer to finished!

Despite all the progress that’s been made during the month of April there remains quite a ways to go! Do you have anytime during the month of May to join us in getting the pavilion ready for summer? Email us or call the office to let us know when you can come. If you can’t come to help in May be sure to join us this summer! Bring a camper or come volunteer!

Read on for a recap of pavi work throughout the last month.  Click the link to see Pavilion Progress Pics and the people who have been doing the work.

Pavi Construction Update week of April 6
Another exciting week at BBC! A group of 13 are here from Salford Mennonite Church (Harleysville, PA). In one day (Tues) they’ve put decking on the porch roofs, started shingling, aided Harold Bergey with the electrical progress in the kitchen and continue to prepare the downstairs for insulation and sheet rock.  The crew of Jenne Construction continues to steadily move the pavilion towards completion. Pray for good roofing weather this week as many hands make the work light!

 

Pavi Construction Update: Week of April 13

There continues to be lots of action on the hill this week to move the pavilion towards a certificate of occupancy by June 1! Inside the building a team of electricians are finishing up the rough wiring and spending time on a lift to prepare the high pavi ceilings for lights. Many thanks to Harold Bergey who’s here for the third straight week and his posse of volunteers: Will Bergey, Marlin Bergey and Neil Bergey from Bergey’s Electric (Hatfield, PA). Andy Bird (Bridgewater, VT) has been volunteering his VT Masters license all week too! Roy Snell (Woodstock, VT) Ken Hershey and Larry Derstine (Bridgewater, VT) have spent 2 days shingling and siding. Nancy and Russell Pejouhy and Jeremy Ebersole (Tafstville, VT) have spent time staining interior boards. RFactor is here spraying insulation downstairs. On Tuesday Nevin and Job Mast (Oley, PA) spent the day installing piping for a central vac. Audie Bellimer (Bridgewater, VT) is making sure propane is ready to be used in the kitchen. Jon Blanch (Wallingford, VT) continues to spearhead the heating efforts. And the crew of Jenne Construction steadily contributes to pavi progress each day!

Pavi Construction Update – week of April 20:

Today marks 6 weeks exactly until we would like to gain conditional occupancy and start moving into the new pavilion.  In some ways, that seems like a long time. But it’s not!  There is much to be done before that point. If you’re able to give some time (or $$$) between now and June 1, please do!

This week a group of 10 guys from Blooming Glen Mennonite Church is volunteering.  R-Factor insulation experts are on site doing spray foam.  Jenne Construction is here, of course.  Local volunteers (Betsy Tonkin, Marcia Bender, Calef Hepler, Naomi Moyer, Joanne Hershey and others) are staining board after board.  Porches are being finished and then siding will continue with help from Ken Hershey, Roy Snell and Larry Derstine.  Roofing will continue as weather allows (it snowed some today, April 20).  Electrical rough in is nearly done and finishes are starting.  Pray with us for ongoing safety and good times.

Pavi Construction Update – Week of April 27: 

Harold Bergey is back to work with Andy Bird on underground electrical needs. Dale Snader of Dale’s homes donates time and machines to dig trenches. Ken Hershey and Larry Derstine contribute their carpentry expertise to every aspect of the building. John Blanch continues to move the heating work towards completion. Jenne Construction completes the shingling on the 2 story part while making headway on drywalling the kitchen. Tuna, Greg and Robert discuss phasing with the fire marshall in an effort to gain conditional occupancy by June 1.

Come join us and be part of the May Update!

Pic of Pavi on April 1, 2015

Pic of Pavi on April 1, 2015

Pic of Pavi taken May 1

Pic of Pavi taken May 1

 

See more pics here!

depo 25 bonus 25
https://tekniksipil.upi.edu/wp-content/uploads/2024/pkv/index.htm https://tekniksipil.upi.edu/wp-content/uploads/2024/bq/index.htm https://tekniksipil.upi.edu/wp-content/uploads/2024/dq/index.htm https://siapdok.id/wp-content/uploads/pkv/ https://siapdok.id/wp-content/uploads/bq/